The Managing Director of the Persian Gulf Fajr Energy Company said: Fajr Co is to add two transformers and then three turbine - generators to the 400 KW substation development plan according to its new plan to develop its power plants in order to increase its power generation and transmission capacity.
Referring
to the implementation phase of the 400 KV substation development project,
Abdollah Alipanah Bahnemiri said in an interview with the reporter of Fajr Co Public
Relations: “Electricity is the most strategic product of Persian Gulf Fajr Energy
Company, which indeed plays a special role in the sustainability of
petrochemical production in the region, as well”.
Reiterating that Fajr Energy Co - along
with its two power plants - has the capacity to generate 1147 Megawatt hours of
electricity, he said: “The electricity generated in the two power plants is
transmitted to the two distribution and transmission stations after boosting the
electrical voltage level of 132 KW, and finally is delivered to the regional companies
or the national electricity network”.
Alipanah said: Along with guaranteeing the stability
of electricity
supply to the petrochemical industries in the Special Economic Zone, the company
also injects 500 MWs hours of electricity (instantaneous power) into the
national network for the comfort of the respectful people of the Khuzestan province
during the hot months of the year.
The substations in the Persian Gulf Fajr Energy Company
are divided into two types of AIS aerial substations and GIS substations. GIS substations are a sort
of electrical switches that consumes SF6 gas to complete the insulation work of
electrical components. This allows us to place several power switches
next to each other in a minimum space.
Pointing out that the AIS aerial power
transmission lines are also located in the 400 KW substation section of the company, the
Managing Director of Persian Gulf Fajr Energy Company said: The two
transformers in this substation - each of which with a capacity of 315 MV
ampere - are set to increase the voltage from 132 KW to 400 KW. AIS aerial substations are also
set to connect the electricity network of the company to the national
electricity network by using the aerial power transmission lines in order to make
the sending and receiving (transmission) of the electricity
possible.
If any of the transformers faces a problem, all electric charges will be transmitted to another
transformer, a process which is always getting monitored and supervised by some
technical experts as already defined in an intelligent program.
Alipanah continued: while any of these transformers is disconnected
from power circuit, an electricity generation turbine will also be removed from the
circuit, as well so that the electrical load on the other transformer get adjusted
based on the capacity of the transformer.
He also continued: Considering the importance of
the aerial substation and increasing the power transmission capacity and also maintaining
the stability of the power generation, the development of the 400 KW substation
is recognized as a strategic need, as well.
In this regard, a strategic project was defined
with the help of an engineering studies consultant, and then the necessary licenses
have subsequently been obtained, too. The project includes some parts such as: designing,
engineering, ordering, manufacturing and then the installation of the transformers,
the GIS gas switches, the cables, the high voltage cables and other peripheral
equipment and also preparing the necessary infrastructures and implementation of some constructional
operations.
The manager of the Persian Gulf Fajr Energy
Company said: At the first stage of the project we ordered two power
transformers with technical characteristics of 400 KW to 132 KW with a power of
315 MWA made
by a
domestic company in order to develop the 400 KW substation. Due to the heavy
traffic nature of the commodity, the power transformers - after manufacturing and
assemblage and also passing the necessary laboratory tests - had been
transferred to Bandar Abbas port through waterways and then to Imam Khomeini’s
commercial port and they finally arrived to destination (the location) of the
400 KW substation. We have ordered the Iranian manufacturers to manufacture them in order to rely more on the
domestic capabilities and show our support to them.
He reminded: Other parts of the project to develop
the 400 KV substation have been carried out after passing the necessary phases
such as designing, ordering and manufacturing with the help of the Iranian and
some non-Iranian manufacturers and then been delivered. We have also obtained the necessary
licenses for the construction and infrastructure sectors and now they are now at
the stage of holding the tender.
Alipanah, the Manager of the Persian Gulf Fajr Energy
Company finally went on by
saying that a new project has been started along with the implementation of the
plan to develop the 400 KW substation, in order to increase the capacity
of the power plant in District 2 through adding 3 turbine generators to the
substation. The project has so far passed the reviewing stage and will start to
select the contractor and start the executive operations after being approved
by the board of directors.